Friday, August 22, 2014

PAC EXPANDS…
Construction Update---August 22, 2014

It’s been several weeks since I shared the groundbreaking of the new south-side addition at PAC.  See the photo to view construction progress!



Construction is on track and our anticipated occupation date is still early spring 2015. 

Our nearly 8000 square foot addition will be at all three PAC levels.  Basement space includes freight entry, file storage, 2 offices and equipment storage.  At the gymnasium level, there will be a vestibule with south-side egress that will include restrooms and a water fountain and much needed storage space for PAC supplies and equipment.  Opening off of the track at PAC’s second level, there will be a large studio room, capable of being divided into two functional spaces.  There will also be a small fitness equipment storage room adjacent to this second story activity space. 

PAC Staff anticipate close to 100,000 total visits in 2014, surpassing 2013’s total of 95,500 visits.  We know this additional storage and program space will greatly enhance patron satisfaction, as more of what the community wants will be available.  Youth and adult activities will be concurrently facilitated during our prime time after school and evening times of the day.  And, equipment will be safely stored out of the way of activity areas.  This will ensure a safer, tidier environment.

We are proud to be able to offer our stakeholders this essential addition to PAC, knowing it will improve our current programs and ensure safe and effective classes, activities and special events far into the future.
 
Look for all our construction updates and activity information on www.pinedaleaquatic.com and the PAC Facebook page.  And, feel free to call at 367-2832 to ask any questions you may have.  Do not hesitate to contact me at:  jhuntley@pinedaleaquatic.com.

As always, PAC strives to make a difference in the community; and to always serve you better.

Thank you for being part of it!
JJ Huntley